Wednesday, November 30, 2011

30/11/2011 - Alex's lights on, more capping, Started to clean inside our house.


Tile fixed in ground floor bathroom.
Da lat gach tuong cho phong tam o tang duoi.


Study cleaned.
Phong lam viec da duoc lam sach.


Bathroom upper floor cleaned.
Da lam sach phong tam o tang tren.


Tuesday, November 29, 2011

29/11/2011 - Alex's box gutter in, blue board on Virginia's side done, more foam our side done.


More foam installed.
Da lap dat tuong phia truoc nha.




More foam installed.
Da lap dat tuong phia truoc nha.



More foam installed.
Da lap dat tuong phia truoc nha.


Foam for study and bathroom upper floor.


More foam installed (south wall).
Da lap dat them tuong (phia Nam).






Monday, November 28, 2011

28/11/2011 - Alex's power, and posts install, more work on his foam and shoji screens as well. A latch and some foam for us as well.




Side finger door pull of shoji screen lounge room installed.
Da lap dat tay nam cua lua phong khach.






















More foam installed.



More foam installed outside for study and bathroom upper floor.
Da lap dat tuong ben ngoai phong lam viec & phong tam o tang tren.


More foam installed outside for study and bathroom upper floor.
Da lap dat tuong ben ngoai phong lam viec & phong tam o tang tren.


Our house view from Church Street.
Tam nhin ve phia nha tu Duong Church.

Friday, November 25, 2011

25/11/2011 - Fan's and electrical continues, Alex's aircon installed, shoji screen, and holes cleaned out.


More foam delivered.



Stairwell fan installed.
Da lap dat quat tran cho cau thang.


Stairwell fan installed.
Da lap dat quat tran cho cau thang.


Fan in bedroom 2 upper floor.
Da dieu chinh do cao cua quat trong phong ngu 2 o tang tren.


Downlights in study installed.
Da lap dat den tran cho phong lam viec.



Strip lights for study bench installed.
Da lap dat den cho ban lam viec.


Stairwell fan installed.
Da lap dat quat tran cho cau thang.


Stairwell fan installed.
Da lap dat quat tran cho cau thang.